Dependencies Configuration

Gantt Charts uses Jira issue links for working with dependencies between issues.

To create issue-to-issue dependencies, you first need to specify the link types you want to use for each dependency relationship.

Setting dependencies in the Gantt Configuration

By default, Finish to Start (FS) dependencies are enabled with "blocks" link type. To learn more about the the available dependency types, see  Dependencies .

If you have the BigGantt add-on installed, your default link type will be "has to be done before."

Adding Dependency and Link Types

You can use multiple dependency relationships and link types within your Gantt chart. To enable a new dependency and/or link type, click the appropriate Add Type button and select the link type you want to use.

Add Link Type to Gantt Configuration

All of the options you select here will be available to you when you create a link using the link button in the toolbar.When you create a link by dragging one task bar to another, if you have more than one link type associated with the type of dependency being created, the one marked as a favorite will be used, or a pop-up will appear for you to select the appropriate type.

Select Finish to Start Link Type

Lead/Lag Time

By default, dependency transitions happen immediately. For example, in an FS dependency, the second item in the dependency starts as soon as the first item finishes. If you need to delay a start/finish or begin it early, you can configure a lead/lag time for each dependency type.

  • To set a lead time, input a negative number.

  • To set a lag time, input a positive number.

Gantt Configuration - Lead and Lag.png

To learn more, see  Dependency Lead/Lag Time .

Favorite

You can specify a default link type for each dependency type by checking the appropriate favorite box.

Favorite Link Types

The "favorite" link types for each dependency type will be displayed in the Type drop down menu when using the New Dependency Menu. To see additional link types, click the View more... link.

View More Dependency Link Types

If you don't have any favorites configured, all link types will be shown.



When you add a dependency within your chart, Gantt Charts creates a link of the corresponding link type between the two issues. See Dependencies for more information about creating dependencies within a Gantt chart.

Gantt Charts also supports dependencies between other types of items, such as folders and pages, but these are stored within Gantt itself.