Gantt Charts for Structure (DC)
Breadcrumbs

Working with Baselines

/*<![CDATA[*/ div.rbtoc1761762472472 {padding: 0px;} div.rbtoc1761762472472 ul {list-style: disc;margin-left: 0px;} div.rbtoc1761762472472 li {margin-left: 0px;padding-left: 0px;} /*]]>*/ Viewing Saved Baselines Hiding Baselines Including Baselines in the Gantt Gadget Exporting Baselines

Viewing Saved Baselines

To compare the current chart to a saved baseline, open the Baseline menu and select the baseline you wish to use.


Open an existing baseline


Baseline Offset

When viewing a chart with a baseline, hover over any item to see how far ahead or behind the baseline schedule the task currently is.

Baseline offset

Hiding Baselines

When a baseline is applied, it's name is displayed in the Baseline menu. 

Current Baseline.png

To hide the baseline (so you just see the current chart), open the Baseline menu and click No Baseline.

No Baseline.png

Including Baselines in the Gantt Gadget

Baselines can be included in  Dashboard gadget s and  Confluence gadgets . To enable baselines, simply select the baseline you want to include in the gadget settings dialogue.

Gadget Option.png


Exporting Baselines

You can include baselines when  exporting a Gantt chart .

Export Gantt to PDF


To include baselines in an export:

  • Make sure the baseline you want to include is visible in the chart before selecting Export Gantt Chart

  • Check the Baseline option in the Gantt Chart Details section of the Export dialogue

  • Select whether or not Baseline delays should be displayed