Gantt Charts for Structure (Cloud)
Breadcrumbs

Precision Configuration

Gantt Charts for Structure allows you to define the precision used for scheduling and calculations. You can choose 1 minute, 1 hour or 1 day precision (1 hour is used by default).

Precision configuration - Cloud.png

Precision defines the minimum meaningful amount of work. All date, time and duration values in your chart are rounded according to the selected precision. When rounding for precision:

  • Start dates are rounded down

  • Finish dates and durations are rounded up

For example, with the default 1 hour precision, a duration of 15 minutes will be displayed in your chart as 1 hour. A Start Date of September 12, 2022 9:45 AM would be shown as September 12, 2022 9:00 AM.

Gantt rounds the value of Jira fields when doing calculations, but the field value itself is not updated.