This article applies to LiquidPlanner Classic. To view the documentation for Portfolio Manager (formerly LiquidPlanner New), visit the Portfolio Manager Help Center .
LiquidPlanner’s predefined reports are located in the Reports Menu on the Projects tab . Click Status to view the Status Report for a selected plan item. To print the report, click the printer icon while in full-screen mode.
With one click, this report provides you with the most vital details about a project, package or sub-folder. It shows you hours logged, hours remaining, percent complete, tasks, milestones and totals by person.