Gantt Charts for Structure allows you to define the precision used for scheduling and calculations. You can choose 1 minute, 1 hour, or 1 day precision (1 hour is used by default).

image2022-12-14_13-46-14.png

Precision defines the minimum meaningful amount of work. All date, time, and duration values in your chart are rounded according to the selected precision. When rounding for precision:

  • Start dates are rounded down

  • Finish dates and durations are rounded up

For example, with the default 1 hour precision, a duration of 15 minutes will be displayed in your chart as 1 hour. A Start Date of September 12, 2022 9:45 AM would be shown as September 12, 2022 9:00 AM.

Gantt Charts rounds the value of Jira fields when doing calculations, but the field value itself is not updated.