Convert an Item | LP Classic Support

This article applies to LiquidPlanner Classic. To view the documentation for Portfolio Manager (formerly LiquidPlanner New), visit the Portfolio Manager Help Center .

The Convert Item feature allows you to quickly change a plan item from one type to another (with some limitations). For instance, if you create a task called “Contract Signed” and decide later that it should be a milestone instead, you can easily convert the task to a milestone and the item’s content will be carried over.

Via the Edit Menu

  1. On the Projects tab, select the item to convert.

  2. Click on Edit Menu > Convert Item.

convert-item.png

Via the Edit Panel

Plan items can also be converted via the Edit Panel:

convert

Allowed Item Types

Below are the plan items that can be converted, and what type of item they can be converted to:

Item:

Can be converted to:

Task

Milestone , Full-Day and Partial-Day Event

Milestone

Task, Full-Day and Partial-Day Event

Full-Day Event

Task, Milestone, Partial-Day Event

Partial-Day Event

Task, Milestone, Full-Day Event

Sub-Folder

Project

Important Notes

Here are some things to keep in mind when converting certain types of plan items:

  • When converting a multiple owner partial-day event into a task, each owner will be given an assignment with an estimate equal to the duration of the event. For example, a multiple-owner partial day event on 12/26 from 9-11am, would be turned into a task with assignments of 2-2 hours for each owner.  If the event is set to recur, the task will have an estimate equal to the duration of all  events in the cycle. For example, a partial-day event set to recur on Mondays and Wednesdays from 9-10 am for 3 weeks would be converted into a task with an estimate of 6-6 hours for each owner.

  • Recurring partial-day events converted into milestones or full-day events will fall on the event’s Start [E].

  • Full day events and milestones assigned to “everyone” that are converted to tasks are “unassigned.”

  • Converting a sub-folder to a project can’t be undone. It is not possible to convert a project back to a sub-folder.